Yesterday and today I spent about 4 hours doing the following:

1. Fabricated a splice piece for the inner left hand fender-took me an hour and 1/2 to complete but it looks good.

2. Went over the 4 fenders and located some more imperfections (on 3 fenders) requiring a additional skim coat-more sanding completed (most of the skim coat removed). I now need to block sand and re-primer

3. Por 15 coated the inner fender wells-front-just in front of the doors. It looks good.

The month has proven to be very productive bodywork wise-now heads down required for early December then I will probably stop working around the 15th. Hopefully I will have all the bodywork completed to final sealer primer...